Approximately 1,067 lots
September 2026 manager report: Phase 1 and 2 road, water and sewer engineering review. Planning and engineering-review scope, not completed homes or a finally buildable total.
Read the manager report · p. 23Local development tracker
What the dated town records establish, and what still needs confirmation.
Town-report snapshot through · Guide prepared .
Town reports describe grading, entrance and utility work at Lennar’s Retreat at Lake Tillery, around Lillys Bridge Road / Lake Tillery Road, Mount Gilead area. The developer lists 524 Livingston Point as the community address.
The October 6 packet still described the sewer force-main crossing as being in permitting. This is a dated record of progress, not a live construction or permit-status feed. Later changes are not confirmed by this summary.
September 2026 manager report: Phase 1 and 2 road, water and sewer engineering review. Planning and engineering-review scope, not completed homes or a finally buildable total.
Read the manager report · p. 23The developer’s Coming Soon listing describes a private boat launch for the community. It is resident-oriented, not a public boating-access point, and this guide does not establish that it or other planned amenities are complete.
Developer’s community listingEarlier plans and reports used different lot counts. Do not add phases together or treat a planning figure as a final approved, buildable or occupied-home total.
Proposed scope, conditional approval, construction activity, testing and final acceptance are different stages.
Session Law 2024-20, section 8, sets the annexation effective date. Annexation does not by itself establish construction completion or occupancy.
Session Law 2024-20 · section 8The minutes retained in the September 2025 packet record conditional zoning approval. That is a different step from final permits, completed infrastructure or occupied homes.
September 2025 packet · August 7 minutes, pp. 2–3The engineering document describes existing lift-station service for the first 275 lots, with up to 435 additional lots conditional on a new station being approved, built and accepted. These historical conditions are not proof that those later steps have occurred.
February 2026 town packet · engineering document, p. 48Phase 1 grading, the sewer tie-in at Lift Station 6 and entrance turn-lane work were reported. Five entrances and commercial uses were planned; the report does not establish that all entrances or uses are open.
April 2026 town packet · manager report, p. 11Public Works reported pressure testing of lines. Testing is a construction milestone, not proof of final system acceptance or occupancy.
July 2026 town packet · June Public Works report, pp. 76–77Phase 1 and 2 road, water and sewer engineering review was described for approximately 1,067 lots. This is not a verified final stamped total or a count of completed homes.
September 2026 town packet · manager report, p. 23The force-main crossing remained in permitting. The town described processing a $5,000 Duke application fee and $2,000 security deposit while coordinating with WithersRavenel and Duke. Processing those items is not proof that a permit was issued or the crossing completed.
October 6, 2026 town packet · pp. 40–41Primary records are linked at their cited PDF pages where available. Document dates remain visible.
Future checks can follow town minutes, Montgomery County planning records and North Carolina DEQ collection-system, AccessDEQ and stormwater permit records.